On a 203(k), closing is only the halfway point. The repair money goes into an escrow account at the single closing, then comes out in stages as the work is completed and inspected. Most 203(k) files that stall do it in that second stage. Here are the HUD Handbook 4000.1 release-of-funds rules, including the June 2026 change to Limited draws, so you can set expectations before closing and keep each draw moving.

What changed in 2026: Limited 203(k) now allows four draws

In 2024 FHA raised the Limited 203(k) cap from $35,000 to $75,000 (ML 2024-13), but each contractor could still be paid only twice. FHA says lenders reported that this disrupted contractor cash flow and raised the risk of delays and abandoned projects. Mortgagee Letter 2026-06 (June 23, 2026, effective immediately) made these changes:

  • Limited: up to four draws per contractor (or for the borrower, if acting as contractor). That means the initial draw at closing, no more than two intermediate draws, and the final draw. A draw may include up to two disbursements and still counts as one.
  • A job that needs more than four draws per contractor is now “major” rehabilitation and belongs in a Standard 203(k).
  • Standard: still five draws (four intermediate and one final). FHA clarified that each draw may include multiple disbursements.

Limited vs. Standard at a glance

Limited 203(k)Standard 203(k)
ScopeMinor, non-structural; up to $75,000 total rehab costMajor and structural work; $5,000 minimum
203(k) ConsultantOptionalRequired (FHA roster)
Maximum draws4 per contractor5 (4 intermediate + final)
Rehab periodUp to 9 monthsUp to 12 months
Proof of completionUp to $15,000: receipts or Borrower’s Letter of Completion. Over $15,000: inspection by the lender or a third party, plus the Letter of CompletionConsultant’s draw inspection on HUD-9746-A
Check payable toContractor alone, or borrower and contractor jointlyBorrower and contractor jointly, unless the borrower authorizes direct payment in writing at each draw
Contingency reserveLender’s discretion, up to 20%10% to 20%, depending on property age and condition

What can be paid at closing

The lender documents the initial draw on form HUD-92900-LT.

  • Standard: permit fees (the permit must be obtained before work starts), prepaid architectural/engineering and consultant fees, origination fees, discount points, materials already paid for under a supplier contract with an order placed, and up to 50% of unpaid materials costs under a supplier contract with an order placed. On contractor disbursements, 10% is held back in the contingency reserve.
  • Limited: permit fees, origination fees, discount points, and up to 50% of estimated materials and labor. The 50% is allowed only when the contractor can’t or won’t wait for payment until the work is done, or when it covers materials bought before construction. A contractor’s statement is enough to document it.

Five draw rules every LO should know

  • No pay for unfinished work. Materials sitting on site generally can’t be paid for until they’re installed. The only exceptions are the supplier-contract cases above.
  • 10% holdback on every draw. It isn’t required when a subcontractor is 100% complete on a work item, the inspector accepts the work, and lien waivers are provided.
  • Lien waivers at every disbursement. For partly finished contracts, that means a partial conditional waiver covering the completed items.
  • Five business days. The lender must release funds within five business days of receiving a properly executed draw request and any needed title update. Missing signatures, waivers or title updates keep that clock from starting.
  • Codes and permits. Funds are released only for work that meets federal, state and local codes, including required permits and inspections.

The contingency reserve, explained

The contingency reserve covers costs nobody could see before the walls were opened. For a Standard 203(k), it is a percentage of financeable repair costs:

  • Under 30 years old: optional, 0% to 20%. Required at 10% to 20% if there is termite damage.
  • 30 years or older: required at 10% to 20%. The minimum is 15% if utilities aren’t operable as noted in the Work Write-Up.

For a Limited, the reserve is optional and set by the lender, up to 20%. On either program the borrower may fund it with their own money. Those funds are tracked separately and can be refunded or applied to principal at the end.

Using it: health or safety items found mid-job must be handled through a change order. On a Standard, using contingency for other improvements before the work is finished requires the lender to determine that new health or safety problems are unlikely and that the loan stays at or below 95% of the After Improved Value. After completion, a change order can put the remainder toward extra improvements, and the lender must answer in writing within five business days. Unused financed contingency goes to principal on a Limited. On a Standard it goes to principal unless approved improvements use it.

The consultant’s role at each draw

On a Standard 203(k), the HUD consultant is the lender’s eyes on the job. At each draw the consultant:

  • inspects the work for completion and quality of workmanship;
  • confirms that permits are on site and the work meets local codes;
  • completes form HUD-9746-A by line item against the Work Write-Up, and makes sure the borrower and contractor sign it before payment is authorized;
  • prepares change orders on HUD-92577. The lender must approve a change order before that work starts, and each item must be 100% complete before it is paid; and
  • reports stoppages of more than 30 consecutive days, deviations from the write-up, and anything that affects eligibility, safety or the structure.

HUD caps consultant fees: up to $375 per draw inspection (reasonable and customary for the area), $120 per change order, $225 per reinspection, and mileage at the IRS rate beyond 15 miles. The consultant’s inspection is not a home inspection, and the consultant-borrower agreement must say so.

Final draw, closeout and the Florida angle

Before final release, the lender needs the Borrower’s Letter of Completion, a certificate of occupancy if the jurisdiction requires one, all required local inspections, the Final Release Notice, and lien releases (or receipts) from every contractor and supplier who could file a claim. On a Standard, the consultant, contractor and borrower also sign the final inspection and draw request. The lender may keep the holdback for up to 35 days, or longer if state law allows more time to file a lien.

In Florida, a claim of lien can be recorded up to 90 days after a lienor’s final furnishing of labor or materials (Fla. Stat. 713.08(5)). A lender must also record the Notice of Commencement before disbursing construction funds to the contractor (713.13(7)). Confirm with your title agent how they handle waivers and title updates.

Deadlines that can trigger default

The rehab period starts at funding. The lender may treat the loan as in default if work doesn’t start within 30 days, stops for more than 30 consecutive days, or isn’t finished on time. An extension requires current payments (or compliance with a forbearance plan), an explanation and a new completion date.

How to keep a renovation file moving: an LO checklist

  1. Tie the draw schedule to real milestones before closing. On a Limited, a job that needs more than four draws per contractor is really a Standard.
  2. Settle the initial draw early. Get supplier contracts, placed orders or the contractor’s statement in the file before closing.
  3. Make sure permits are pulled before work starts.
  4. Brief the contractor on the 10% holdback and lien waivers so cash flow never surprises them.
  5. Submit complete draw packages: the signed HUD-9746-A, partial conditional lien waivers, and a title update if one is required.
  6. Change order first, work second. Unapproved scope changes are a common reason draws get held.
  7. Calendar the deadlines: the 30-day start, any 30-day stoppage and the completion date. Request extensions before they’re needed.

Frequently asked questions

Does a Limited 203(k) need a consultant?

No, but one may be used, and since ML 2024-13 the consultant’s fee can be financed on a Limited. Jobs over $15,000 still need a lender or third-party inspection.

Can a draw pay for materials delivered to the site?

Generally no. Materials must be installed first, except for the supplier-contract cases described above.

Who approves the use of contingency funds?

The lender, in writing. On a Standard, the consultant prepares the change order.

Need a consultant on your next 203(k)?

Quality Real Estate Inspections handles HUD 203(k) feasibility studies, Work Write-Ups, draw inspections and change orders across Central Florida. For more background, see what a 203(k) consultant does, the Limited vs. Standard 203(k) loan explainer, buying a fixer-upper with a renovation loan, and insuring a home under renovation.

Questions about a 203(k) file? Call 321-222-3116 or visit our FHA 203(k) Consultation page.

By Tariq AbouAdma, HUD 203(k) Consultant (A1331) and Certified Master Inspector (HI9899), Quality Real Estate Inspections LLC, 336 Wilshire Blvd, Suite 274-229, Casselberry, FL 32707.

Sources

This is an educational summary of HUD requirements, not legal advice or a loan commitment. Lender overlays may be stricter, so confirm requirements with the lender on the file.