Most loan officers know a 203(k) Consultant is required on a Standard 203(k). Fewer have a clear list of what that consultant hands back, and which of those items HUD expects you to check before underwriting. HUD Handbook 4000.1 spells it out. This guide maps the consultant’s duties to the documents that land in your file and the points where the lender, not the consultant, is responsible.

Key takeaways

  • A consultant is required on every Standard 203(k) and may be used on a Limited. Any consultant must be active on the FHA 203(k) Consultant Roster for the property’s state (Handbook II.A.9.a; II.A.8.a.v(B)).
  • HUD lists the consultant’s duties as deliverables: Feasibility Study (on request), property inspection report, architectural exhibits, Work Write-Up and Cost Estimate, draw inspections, change orders and progress reports (II.A.9.b).
  • The lender must verify that the name on the Consultant’s Certification matches the consultant selected (II.A.8.a.vi(C)).
  • HUD requires the lender to evaluate and document each consultant’s performance, including a review of actual work product, at least annually (II.A.8.a.xix).

What the consultant delivers, in file order

DeliverableWhat HUD saysHandbook
Feasibility StudyPrepared if the borrower or lender requests it. A preliminary inspection plus an estimate of materials and cost to meet HUD requirements. If one was done, the lender must obtain a copy.II.A.9.b.i, II.A.9.h; II.A.8.a.xiv(A)(5)
Property inspection reportOn-site inspection by the consultant personally, using the 35-point checklist, certifying the condition of electrical, plumbing, heating, roofing and structural systems.II.A.9.b.ii, II.A.9.e
Architectural exhibitsConsultant identifies all required exhibits and prepares them, or gets them from a qualified subcontractor. The lender must obtain and review them.II.A.9.b.iii; II.A.8.a.xiv(B)(2)
Work Write-Up and Cost EstimateUnbiased, prepared without using the contractor’s estimate. Each Work Item flagged as MPR/MPS-required, structural or a borrower elective. Permit-required items marked. Labor and materials itemized separately.II.A.9.b.iv, II.A.9.g
Consultant’s CertificationSigned after preparing or reviewing the Work Write-Up and Cost Estimate, including no identity-of-interest or conflict-of-interest.II.A.9.k.i; II.A.8.a.xiv(A)(1)(b)
Consultant/Borrower AgreementWritten agreement explaining services and fees per service. It must disclose that the consultant’s inspection is not a “Home Inspection.”II.A.9.k.ii; II.A.8.a.xiv(B)(3)
Draw request (HUD-9746-A)Completed at each draw inspection; consultant checks completion against the Work Write-Up, local codes and required permits and inspections.II.A.9.i, II.A.9.k.iii(A)
Change order (HUD-92577)On request, the consultant reviews the proposed change and costs it. Work cannot proceed until the lender approves.II.A.9.j, II.A.9.k.iv
Progress reportingConsultant informs the lender of stoppages over 30 consecutive days, significant deviations from the Write-Up, and eligibility or safety issues.II.A.9.b.vii

Where the file is still yours

The consultant prepares the paperwork. HUD keeps these tasks with the mortgagee:

  • Select from the Roster. Pick a consultant active for the property’s state and enter the Consultant ID at case number assignment. HUD tells lenders not to use a consultant with demonstrated poor performance in the lender’s reviews. On a Limited with no consultant, enter “203KS” (II.A.8.a.v(B)).
  • Match the names. Verify that the name on the Consultant’s Certification matches the selected consultant (II.A.8.a.vi(C)).
  • Collect the Identity-of-Interest certifications. The borrower and the consultant each sign one, placed in the case binder. If the borrower chose a consultant for the Feasibility Study, the lender may select that same consultant for the project without creating an identity of interest (II.A.8.a.xiv(A)(1)).
  • Add appraiser findings. If the appraisal flags health and safety repairs missing from the Work Write-Up, they must be added to the consultant’s final Write-Up (II.A.8.a.xiv(A)(3)).
  • Set the rehab period. On a Standard, the lender reviews the Work Write-Up to set the time frame, not to exceed 12 months (II.A.8.a.xv).
  • Authorize draw inspections and manage the escrow. The Handbook says the mortgagee is fully responsible for this. Before the final release on a Standard, the lender approves the final inspection and draw request signed by the consultant, contractor and borrower (II.A.8.a.xviii).
  • Review the consultant annually. Standards for consultant performance belong in your Quality Control Plan, and you must document an annual evaluation that includes the consultant’s actual work product (II.A.8.a.xix).

Feasibility Study: a question to ask early

If a file may not pencil out, a Feasibility Study answers that before the full Work Write-Up. HUD’s fee schedule allows up to $375 for it (II.A.9.c.i). It is financeable on a Standard when needed to determine feasibility, and not financeable on a Limited (II.A.8.a.vi(D); vii(G)). Because the consultant who did the study can be chosen for the project without an identity-of-interest problem, the early work is not wasted.

Consultant fees HUD allows

These are HUD’s maximums (II.A.9.c). Actual fees vary by consultant and area, and the Consultant/Borrower Agreement must state them.

  • Work Write-Up and exhibit review: up to $1,000 (repairs up to $50,000), $1,200 ($50,001–$85,000), $1,400 ($85,001–$140,000), and the lower of 1% of repair costs or $2,000 above $140,000; plus $25 per additional dwelling unit
  • Draw inspection: reasonable and customary for the area, no more than $375 each
  • Change order: $120 each. Reinspection: $225. Mileage at the IRS rate if the consultant’s office is over 15 miles away

Loan officer checklist

  1. Confirm the program type (Limited or Standard). Use our Limited vs Standard screen if it is close.
  2. Check the consultant’s Roster status for the property’s state before you assign the case number.
  3. Get a signed Consultant/Borrower Agreement with services and fees listed.
  4. Decide whether to order a Feasibility Study first.
  5. When the Work Write-Up arrives, confirm: itemized labor and materials, permit flags, MPR/MPS vs elective labels, architectural exhibits, and a signed Certification with the right name.
  6. Send the final Write-Up to the appraiser and reconcile any appraiser repairs.
  7. Collect both Identity-of-Interest certifications for the binder.
  8. Set the rehab period from the Write-Up (12 months maximum on a Standard).
  9. Plan for each draw: HUD-9746-A signed, permits on site, change orders approved before work.

For the draw mechanics, see our draw schedule guide. For loan sizing, see the maximum mortgage guide. Borrowers can start with What Does a HUD 203(k) Consultant Do?

FAQ

Is the consultant’s inspection a home inspection?

No. HUD requires the Consultant/Borrower Agreement to disclose that it is not a “Home Inspection,” as described on form HUD-92564-CN, For Your Protection: Get a Home Inspection (II.A.9.k.ii).

Can I use the same consultant for the feasibility study and the project?

Yes. If the borrower selected the consultant for a Feasibility Study, the lender may select the same consultant for the project without creating an identity of interest (II.A.8.a.xiv(A)(1)).

Can the consultant use the contractor’s bid for the Cost Estimate?

No. HUD requires an unbiased Work Write-Up and Cost Estimate prepared without the use of the contractor’s estimate (II.A.9.b.iv).

Does a Roster listing mean FHA endorses the consultant?

No. HUD states that Roster placement means only that the consultant met the qualifications. It is not a warranty or endorsement of the consultant or the work (I.B.2).

Related reading: how 203(k) renovation money gets paid, buying a fixer-upper with a renovation loan, and insuring a home under renovation.

Need a consultant on your next file?

To talk through scope, timing or the paperwork above, request a 203(k) consultation or call Tariq AbouAdma at 321-222-3116. Quality Real Estate Inspections LLC, HUD 203(k) Consultant A1331 · Certified Master Inspector HI9899.

General education only, not legal advice. HUD guidance and your lender’s overlays govern each file. Handbook references checked 2026-11-20.

Sources

  • HUD Handbook 4000.1 (Update 18, last revised 8/12/2026): I.B.2; II.A.8.a.v(B), vi(C)–(D), vii(G), xiv, xv, xviii, xix; II.A.9.a–k

Site Map